Waterford-Halfmoon Union Free School Construction Project

Waterford, New York

Project Website
Project Page for the Waterford-Halfmoon Union Free School District K - 12 campus Additions and Renovations Project. Any questions about your project? E-mail me at shows@showsleary.com

 

December 2006:

The science wing addition is taking shape. The foundation is completed. The structural steel is complete with the roof deck in place. The rubber membrane roof has been installed. The brick work on the exterior is completed. The interior slab is poured. Most of the windows are installed. The trades are doing their rough ins: water and heat pipe and vents, unit ventilators and cabinet heaters. Conduit for electrical services is also being roughed in.

Work for grading has begun on the courtyard area. Sidewalks and small assembly area are rough graded.

 

.

 

 

 
 
   
   
   
   
   
   

 

The Architect: Dodge Chamberlin Luzine Weber Associates   www.dclw.com

Project Architects: Hana Panek, Roy Hasbrouck,    phone: 518-479-4000

Construction Administrator: Robert Spencer

 

Special Inspections and Testing: Ryan Biggs

Project Manager: Mike Miller

Project Manager: Chris Lesher

Testing: Don Trojak

 

General Construction Contractor: Greco Construction

Project Manager: Chris Harkin

Superintendent: Mike Martin

Plumbing Contractor:  DiGesare Mechanical

Project Manager: Chris Zimmer

Superintendent: Joe Farrell

HVAC Contractor: Campito Plumbing and Heating

Project Manager: Carol Henry

Superintendent: Ron Liuzzi

Electrical Contractor: Schenectady Hardware and Electric

Project Manager: Tom Lynch

Superintendent: Jason Sanford

Communications/Telephone:

Project Manager: Charles Grolley

Superintendent: Mike Shaninger

Asbestos Abatement: Atlantic Environmental

Project Manager: John Miller

Superintendent: Ken Wall

Monitor PSI, David Foote.